Roughly 1,400 square metres of floor across a large new build house in Hale, Cheshire, with underfloor heating throughout. Every heated zone in the house was poured at an average 80mm of fibre reinforced screed over the pipework. The first floor is complete, with the finished marble staircase under protective covering while the rest of the house is finished around it. The balconies are going down in Retanol fast-drying screed to falls, running from 120mm down to 80mm so water sheds the right way, with the remaining balconies screeded once the scaffold comes down, and the garage got its own 90mm Retanol floor.








Priming, liquid screed and sand and cement walkways for three new padel courts in a converted steel factory.

A 90 m² external balcony laid to falls in Retanol fast-drying screed on a new build in the countryside at Pott Shrigley, Cheshire.

40mm Retanol fast-drying screed over a visqueen membrane in a new glass summer room extension in Bromley Cross, Bolton.